STATEMENT:
CONVERSION OF ALL 191 SEMI-PERMANENT TIMBER (SPT) BRIDGES TO PERMANENT RCC BRIDGES
MOTTO:
TO
DECLARE JORHAT AS NO-SPT BRIDGE DISTRICT BY 2006 FOR FAST AND RELIABLE RURAL
COMMUNICATION.
VEHICLE:
BRIDGES
COST LESS THAN RS 8 LAKHS BE DONE BY FUNDS AVAILABLE UNDER ZP/AP/MP/MLALAD FUNDS.
BRIDGES COST
MORE THAN RS 8 LAKHS BE DONE BY FUNDS FROM NLCPR/RIDF
ROAD MAP &
MILESTONES:
The
whole plan is devided into IV PHASES AS:
YEAR
2003-2004:
PHASE I
YEAR
2004-2005:
PHASE -II
YEAR
2005-2006:
PHASE -III
YEAR
2006-2007:
PHASE -IV
Target
Date |
Mile
stone |
Agency
responsible |
NOVEMBER
2003 |
ü Identification
of funds from MP/MLA LAD/ ZP/AP for the bridges costing less than Rs 8 lakhs |
ü DC ü PD ü CEO,
ZP ü SE,
PWD (R) |
MARCH
2004 |
ü Initiation
of bridges conversion identified for 2003-2004 under NLCPR/RIDF/Local resources (PHASE-I) |
ü CEO,
ZP ü SE,
PWD(R) |
MARCH
2005 |
ü Completion
of bridges initiated in March 2004 and initiation of new works for the year 2005-2006
(PHASE II) |
-do- |
MARCH
2006 |
ü Completion
of bridges initiated in March 2005 and initiation of new works for the year 2006-2007
(PHASE III) |
-do- |
MARCH
2007 |
ü Completion
of bridges initiated in March 2004 and initiation of new works for the year 2006-2007
(PHASE IV) |
-do- |
COMPONENT
MANAGEMENT PROTOCOL/DETAILED ACTION PLAN:
Will be
prepared by 30.09.2003 for PHASE wise conversion as per the fund availability under
RIDF/NLCPR/Local resources.