SEVENTH VISION


STATEMENT:
IMPROVEMENT OF CIVIC AMENITIES IN JORHAT TOWN
MOTTO:
TO DEVELOP JOINT OWNERSHIP OF THE CHANGE PROCESS BY THE CITIZENS AND THE GOVERNMENT
VEHICLE:
MATRI JORHAT- MOR JORHAT

ROAD MAP & MILESTONES:
 

S.No.

Target Date

 

Mile stone

Agency responsible

 

1

31 Dec 2003

ü      Traffic management jointly with community as partner

SP/JMB

2

Dec 2003

 


March 2005

ü      Initiation works of BB Market at the cost of Rs 2.00 Crores under IDSMT
 ü      Completion of Project

District IDSMT Committee

3

Dec 2003

ü      Lighting every required post by street lights with community Participation under PUHOR

JMB

4

31 March 2004

ü      Completion of Improvement works of AT Road with Rs 2.00 Crores

PWD

5

31 March 2004

ü      Garbage Disposal with community as partner

JMB

6

31 March 2004

 

Sep 2004

 

 

March 2005

 

October 2005

 

March 2007

 

March 2010

ü      Completion of feasibility study of River Brahmaputra for drinking water

ü      Preparation of Project report

 

ü      Identification of Funds & Schemes

 

ü      Initiation of the Project

 

ü      Completion Phase-I

 

ü      Completion Phase -II

District Administration/JMB/JDA/Government

7

 

31 March 2004

 

  

18 Nov 2004

ü      Completion of Phase-I of Development of Tinikonia Pukhuri

 

ü      Completion of Tinikonia Pukhuri Project

District administration

8

Dec 2003

 

 

 

March 2005

ü      Initiation of River Front Development works at Puja dhubi under IDSMT

 

ü      Completion of River Front Development works at Puja dhubi

Town & Country Planning

9

 

Dec 2003

 

 

 

 

March 2004

ü      Completion of Phase-I works of Boat Club Development at Tocklai at a cost of Rs 10.00 lakhs

 

ü      Completion of Phase-II works of Boat Club Development at Tocklai

ZP

 

10

 

March 2004

 

 

 

 

March 2006

ü      Completion of Phase-I works of Botanical Garden at Chenijan (Science College)

 

ü      Completion of Phase-II works of Botanical Garden at Chenijan (Science College)

District administration

 

11

Dec 2003

ü      Initiation of works of Drainage works Phase-I (Rs 5.25 Crores) under NLCPR and completion by March 2005

Town & Country Planning

12

March 2005

ü      Initiation of works of Drainage works Phase-II  under NLCPR & Completion by March 2008

-do-

13

March 2004

ü      Initiation of works of Harijan Colony at the new site and completion by March 2006

-do-

14

March 2006

ü      Development of Recreation Park at the Rajamaidam Harijan Colony site and completion by March 2007

-do-

15

March 2005

 

 

 

March 2004

ü      Construction of Cricket Pavillion at the cost of Rs 120 lakhs

 

ü      Construction of Swimming Pool at a cost of Rs 200 lakhs

Stadium Development Committee

 

Jorhat Swimming Pool Construction Committee

16

March 2004

ü      Construction of Bahadur Gaon Burah Senior Citizen Park at Public Bus stand

Bahadur Gaon Burah Smirti Smarakshan Samiti

17

March 2006

ü      Shifting of Truck Stand

JDA/JMB/District admn

  

COMPONENT MANAGEMENT PROTOCOL/DETAILED ACTION PLAN:

Will be prepared by September 2003